Repaving work on the sun decks resumes at The Royal Haciendas 

Work to replace sun deck tiles with the new concrete flooring has resumed at The Royal

Haciendas and will continue in the coming months according to this schedule:

Week 16-25

Three areas of the Phase 2 sun deck will be resurfaced during this period.

Week 25-31

Work will be suspended during the summer vacation period.

Week 32-46

Work will resume in Phase 2 and in Phase 1. During Maintenance Week, gardeners will also be working on new landscaped areas in Phase 1 that are part of the overall sun deck design.

The goal is to complete 5,193 square meters of concrete flooring and 2,815 meters of decorative trim on both sun decks this year (weather permitting), leaving only minor details to be finished in 2023.